On-Going Works
S. No | Description of Works | Name and Address of Employer |
---|---|---|
1 | Filling at peripheral area of Lagoon-I, C&D zone of Stage-II dyke (Phase-VI) at TSTPS | NTPC Ltd., Talcher Super Thermal Power Station PO: Deepshikha, Distt. Angul |
2 | 1st Raising of Arkha Ash Dyke for FGUTPP, Unchahar Distt. Rae Barelli(UP) | NTPC Limited, Feroz Gandhi Unchahar Thermal Power Project, Unchahar |
3 | Ash Dyke Package for Teleangana Super thermal Power Project | NTPC Ltd. |
4 | Designing, Constructing, Commissioning and Testing of 3 Nos. RCC Storage & Sedimentation (S&S) tanks for Water Treatment Plant Village Chandu Bhudera, District Gurugram, Haryana | HUDA, Gurugram |
5 | Balance work of Ash Dyke Package for Meja TPP | Meja Urja Nigam Pvt. Ltd. (A Joint Venture of NTPC & UPRVUNL) Meja, Distt. Allahabad: |
6 | Provision of 1 MW Solar Power Plant at, MES Jhansi | MES, BHOPAL |
7 | Ash Dyke and Raw Water Resorvior works for Jawaharpur Project (2 x 660), Doosan Power Systems India Pvt. Ltd. | Doosan Power System India Pvt. Ltd. Gurugram |
8 | Civil works of First Raising of Ash Dyke (L- IV) from 10.5 RL to 15.5 RL at NTPC Simhadri | NTPC Ltd. Simhadri Super Thermal Power Station PO: Simhadri, Distt. Vishakhapatnam |
9 | Providing and laying of balance distribution pipe line for zone-IV, V, VI, VII & part Zone- VIII covering Sec-58 to 115, Gurugram. “Providing, stringing out, jointing, cutting & testing of DI pipes of size 200mm to 800mm i/d and MS pipe line 1100mm providing and fixing sluice valves, air valves and construction of sluice valves haudies for Zone-VII & VIII, Gurugram and Zone-V (Partial) all other works contingent thereto.” (including maintenance for 3 years and including defect liability period-free of cost) | Gurugram Metropolitan Development Authority (GMDA), Gurugram |
10 | Raising of ash Dyke For Anpara Thermal Power Station | UP Rajya Utpadan Nigham Limited , Anpara(U.P) |
11 | Starer ash Dyke For Brauni Thermal Power Station , District Begusarai , Bihar | NTPC,Ltd |